Construction Timelines [PDF]

The preliminary design and planning began in November 2016. Preliminary individual project timelines are as follows:

Project 

Approximate Start of Planning and Design

Estimated Completion

Greenland Elementary

November 2016

August 2017

Park Lawn Elementary

November 2016

August 2017

Ixonia Elementary

November 2016

August 2018

OHS Main Campus

March 2017

August 2018

Meadow View Elementary

March 2017

August 2019

OHS East Campus - Instructional

March 2017

August 2018

OHS East Campus- District Office

April 2019

February 2020

 

This is a graphic representation of the project phases (PDF):

 

Estimated Facilities Project Timeline