OASD Building Our Future Project Logo

We remain committed to open and transparent communication with you and our community as we develop all of these projects.  To that end, we will be providing regular construction updates, along with photos and other visuals on the OASD website as work on them begins. We hope you will enjoy following the progress on the projects our community so generously supported!

Live Feed Project Updates:  Ixonia Elementary

Click here


December 8, 2017

Facilities projects at Meadow View Elementary, Ixonia Elementary and Oconomowoc High School Main and East Campus are on-track with the original referendum timeline.

Meadow View Elementary Update:  The Meadow View Elementary project is still in the design development and construction document phase.  Interior space design is being evaluated and changes are being made as needed.  The City of Oconomowoc has also made significant progress on the site infrastructure.

Ixonia Elementary Update:  The shape of the Ixonia Elementary addition is well defined and the wood timbers, which are the focal point of the main entrance, are now in place.  

OHS East Campus Update:  A wall breaking celebration was held at OHS East Campus on December 1, 2017.  Demolition and asbestos abatement crews are currently preparing the site for the public bidding phase, which will be held in January 2018.

Learn more about the progress at Ixonia Elementary, Meadow View Elementary, OHS Main Campus and OHS East Campus in the December 8, 2017, Facilities Construction Update [PDF].


November 30, 2017

Design Update: Meadow View Elementary [PDF]

Meadow View Design Process Update

 


November 17, 2017

Facilities projects at Meadow View Elementary, Ixonia Elementary and Oconomowoc High School Main and East Campus are on-track with the original referendum timeline.

At Ixonia Elementary, the concrete floor pad is complete and new classrooms are almost fully framed.  Steel decking for the roof is complete in all available areas and installation of the fire pump and shaft for the fire suppression system was completed last week.  At Meadow View Elementary, the design development and construction document phases of the project are underway.  Interior space design is being evaluated and changes are being made as needed.  Selection of exterior finishes has also begun.  At their November 14, 2017, meeting, the School Board approved the Early Bid Package Award Recommendation for OHS East Campus, allowing interior demolition and asbestos abatement to begin in December 2017.

Learn more about the progress at Ixonia Elementary, Meadow View Elementary, OHS Main Campus and OHS East Campus in the November 17, 2017, Facilities Construction Update.


Join Us to Celebrate the OHS East Campus Project Kickoff!

The OHS East "Wall Breaking" event will take place on Friday, December 1, 2017, at 1:30 p.m. at the OHS East Campus site.  OASD staff, parents, and community members are all welcome to join in the festivities, acknowledgments and student participation.  Click here for event flyer [PDF].

OHS East Campus "Wall Breaking" Event Invitation


October 27, 2017

Facilities projects in the OASD are progressing and timing is on-track with the original referendum timeline.  Learn more about the progress at Ixonia Elementary, Meadow View Elementary, OHS Main Campus and OHS East Campus in the October 27, 2017, Facilities Construction Update [PDF].


 October 13, 2017

Design Update:  OHS East Campus [PDF]

OHS East Campus Design Update Flyer


September 18, 2017

Greenland Elementary held a celebration of construction completion last Friday, September 15.  All of the Greenland students learned and sang a special song to thank the community, construction teams and staff for making Greenland an even better place to learn. 



September 8, 2017

YOU ARE INVITED to a Special Construction Completion Event!
Join Us to Celebrate the Greenland Elementary Construction Completion; Featuring the Greenland Stars!

September 15, 2017 @ 2:30 p.m. 
Greenland Elementary School 
440 Coolidge Street, Oconomowoc, WI 53066

No RSVP required.

Greenland Elementary Construction Celebration Invite

YOU ARE INVITED To a Special Construction Completion Event!
Join Us to Celebrate the Park Lawn Elementary Construction Completion; Featuring the Park Lawn Panthers!

September 29, 2017 @ 8:45 a.m. 
Park Lawn Elementary School 
300 Park Lawn Street, Oconomowoc, WI 53066

No RSVP required.

Park Lawn Elementary Construction Celebration Invite


August 25, 2017

Greenland and Park Lawn Elementary Schools are ready for the start of the new school year!  Construction is complete at both locations and final cleaning and painting will conclude this week.  

Interior cleaning and classroom setup are nearly complete at Ixonia Elementary and installation of the temporary main entrance and ramp are complete as well.  Footings and poured walls for the new addition will be complete this week with structural steel delivery will start next week.  The new addition will start to take shape as the steelwork begins in September.  There will be some new routines at school this year as a result of the construction.  Additional information can be found on the Ixonia Elementary School page.

Facilities Construction Update for the Week Ending August 25, 2017 [PDF]


August 11, 2017

Roof replacement is complete at Greenland Elementary and has begun at Park Lawn Elementary, with completion at the end of the month.  The majority of the interior construction at both locations will be completed next week and classroom cleaning is underway, all in preparation for teachers to access their classrooms the week of August 21, 2017. 

Exterior work on the new Ixonia Elementary School addition is underway and footings are nearly 60% complete.  The temporary front entrance door is being installed and this entrance will be used for the 2017-18 school year while construction continues on the South side of the building.  Asbestos abatement and classroom cleaning will be completed the week of August 14th in preparation for the start of the school year.

Facilities Construction Update for the Week Ending August 11, 2017 [PDF]


July 28, 2017

Construction at Greenland and Park Lawn is nearing completion with classroom ventilation systems and piping finishing in early August.  Exterior excavation continues at Ixonia as crews prepare to begin footings for the new addition in early August. The design development and construction document phases continue for Meadow View Elementary and Oconomowoc High School Main and East campus.  Please click on the link below to access the current construction update with more details on each project.

Facilities Construction Update for the Week Ending July 28, 2017 [PDF]


July 14, 2017

Construction work at Greenland, Park Lawn, and Ixonia Elementary Schools are well underway, with the Greenland and Park Lawn projects on-track for completion in August.  Visioning and schematic design continue for Meadow View Elementary School and Oconomowoc High School Main Campus and East Campus.  Please click on the link below to access the current construction update with more details on each project.

Facilities Construction Update for the Week Ending July 14, 2017 [PDF]


June 29, 2017

The Greenland, Park Lawn and Ixonia Elementary School projects have begun and regular updates on these construction projects are now available.  The Meadow View Elementary and Oconomowoc High School projects are not at the construction phases yet but visioning and schematic design work are underway.  Please click on the link below to access the current construction update.

Facilities Construction Update for the Week Ending June 30, 2017 [PDF


June 9, 2017

The school year is coming to a close but construction work at Greenland, Park Lawn, and Ixonia Elementary Schools are gearing up.  Greenland and Park Lawn projects will include replacement of the heating, ventilation, and mechanical systems along with adding cooling systems.  This work will begin immediately after school ends in June and will be complete by mid-August, prior to the start of the 2017-18 school year.

Likewise, construction work at Ixonia Elementary will begin immediately after school ends in June and will be completed in August 2018 for the start of the 2018-19 school year.  The project includes an addition that will house new classrooms, a cafeteria and school offices.  A new main entrance, some internal classroom renovation, and expansion of the outside play area are also included in the project. 

Starting in late June, you will find bi-weekly updates of the progress on these projects.


May 19, 2017
Ixonia Elementary Ground Breaking Ceremony

Ixonia Elementary School students, staff and families joined with the Ixonia community to celebrate the groundbreaking of the Ixonia Elementary School addition. The OHS Pep Band started off the celebration along with the school mascot, Fiona the Falcon. Ixonia Principal Stacy Yearling greeted students and guests and thanked the community for their continuous support of Ixonia Elementary. OASD Superintendent of Schools Roger J. Rindo echoed appreciation for the community's support of Ixonia Elementary and OASD. He also thanked all of the community, School Board, town and state officials who helped make the project possible.

Students from each grade level shared their hopes and dreams for Ixonia Elementary now and into the future as they contributed items to a time capsule that will be opened by Ixonia students 25 years from now. Students and staff then concluded the ceremony by singing a new rendition of the Ixonia Elementary School song, written especially for the groundbreaking ceremony.



April 24, 2017:
Join Us to Celebrate the Ixonia Elementary School Project Kickoff; Featuring the Fantastic Falcons!

The Ixonia Elementary School Ground Breaking event will take place on Friday, May 19, 2017, at 11:00 a.m. at Ixonia Elementary.  OASD staff, parents, and community members are all welcome to join in the festivities, acknowledgments and student participation.  Click here for event flyer [PDF]


March 9, 2017:  

Building Our Future Project Update [PDF]

Design Update:  Ixonia Elementary School [PDF]

Public Bidding Phase Information [PDF]


January 31, 2017:  Ixonia Elementary Addition & Renovation Schematic Design

  • We continue to be on schedule with the heating, ventilation, cooling, and mechanical system updates to Greenland and Park Lawn.  Design development is underway as engineers are planning for the installation of unit ventilators in classrooms and a number of approaches to both heat and cool the common areas in those buildings.  The project is on budget and will be bid in early April.  Work on the project will begin immediately after school is finished in June with project completion planned for the start of the 2017-18 school year in September.
  • The School Board has taken action to secure a contract to acquire 20.2 acres of land for the new Meadow View Elementary, approximately a mile south of the current school site off of Brown Street/Hwy P.  Our collaborative efforts with the City of Oconomowoc and St. Matthews church continue with regard to planning and development of our new school site, a new St. Matthews School, and a planned regional city park.  Schematic design work on the new school begins next week!
  • Last night the School Board approved the schematic design for the new addition and renovation of Ixonia Elementary School.  Several renderings of the new exterior, as well as floor plans for the addition and renovation, are attached here for you. The project is on budget and will be bid in mid-April.  Work on the project will begin immediately after school is finished in June, and will be completed in August 2018.
  • Planning for the renovation of the classroom spaces at OHS Main Campus as well as the East Campus renovation will begin in March.
W360 N7077 Brown Street
Oconomowoc, WI 53066
262-560-1115
powered by finalsite